Revenue Recognized by Percentage of Completion
Finds: revenue to record on a long contract.
When to use it: Use it for long contracts such as construction, where revenue is recognized as the work progresses rather than all on completion.
The formula
In words: Revenue to date = Contract price x (Costs to date / Estimated total costs)
What each symbol means
| Contract price | Total price agreed for the project | money |
| Costs to date | Costs incurred on the project so far | money |
| Estimated total costs | Total costs expected for the whole project | money |
| Revenue to date | Revenue recognized from the start up to now | money |
Worked example
A builder has a contract for 1,000,000 with an estimated total cost of 800,000. Costs to date are 300,000 and 150,000 of revenue was recognized in earlier periods. How much revenue is recognized this period?
| Percentage complete | 300,000 ÷ 800,000 | 37.50% |
| Revenue to date | 1,000,000 × 0.375 | 375,000 |
| Revenue this period | 375,000 − 150,000 | 225,000 |
The answer
The project is 37.50% complete, so revenue to date is 375,000 and the revenue recognized this period is 225,000.